Case studies / Rail Infrastructure
Corporation
Rail
Infrastructure Corporation (RIC) was the owner of the NSW State Rail Network. It
has the right to use the network to the two main Rail Operators, State Rail and
Freight Australia, as well as other smaller operators. One of its key
responsibilities was to ensure that the Network is used safely. RIC
undertook to completely overhaul its track-use related safety processes and
associated documentation.
Collectively
known as the ‘Safeworking Rules’, this safety documentation is relied on by
all the organisations working on and around the tracks. This includes not only
employees of the rail operators, but also all those maintaining the tracks,
overhead wires, signalling equipment, and so on. The Safeworking Rules are the
touchstone for all track-related safety activity and RIC Management had become
increasingly concerned about their adequacy. As result it undertook an ambitious
project to comprehensively review and upgrade the Rules.
|
The project gained urgency when a rail disaster occurred at Glenbrook in the Blue Mountains west of
Sydney. The subsequent enquiry
found that one of the contributing factors was confusion over the correct safety
practices to follow, which was caused by a lack of clarity in the information
available to drivers, signallers, and train controllers. |
|
65%
reduction in the number of safety incidents |
After two years of intensive
effort, the project produced a revised set of Safeworking Rules that were
universally applauded as much clearer, more concise, and much easier to
understand than those they replaced. They provided a more effective basis for
training, and the easier-to-read manuals gave field workers clear and
unambiguous guidance. As part of the project, 11000 rail workers were retrained
using the new Rules.
The result to date has been a stunning 65%
reduction in the number of safety incidents on the
NSW rail network.
Realisation (then called HCi) won the keenly contested tender. Realisation was selected because of its record as a
specialised consulting firm that had worked successfully with many large
Australian household names, its experience in quality management, and its
capacity to field and support a large team.
Realisation was also chosen because of its
willingness to work flexibly with RIC to help them implement an appropriately
tailored approach, rather than attempt to impose a rigid, externally-derived
methodology.
Development
methodology
The Project Leaders settled on a development
methodology that involved these steps:
-
dividing the required information into new, more logical, subject
areas, such as ‘Work on track’ and ‘Train control’, that would give
readers instant insights into its scope
-
deconstructing the existing documentation and reclassifying it in
the new subject areas
-
weeding out superfluous information and either disposing of it or
sending it on to other areas responsible
-
devising and writing-up new rules based on SME input
(incorporating relevant existing information)
-
guiding the new rules through a review and approval process with
key stakeholders (field representatives, Rail Operators, the Unions, etc)
-
re-writing the information to incorporate review feedback
-
tracking the transformation of the old rules into the new to
provide an audit trail
-
doing regular quality checks, including development process
reviews, readability measurements, and usability tests
By processing all the old information through
the new subject area framework using this methodology, and by filling
information gaps that became evident along the way, the project team was able to
complete its task in the smoothest, most time-efficient way possible. Testimony
to the robustness of the methodology, and the dedication of the team applying
it, is the fact that the project was completed right
on time against an ambitious set of deadlines.
This was a commendable result given the
number of stakeholders involved and their separate political agendas, as well as
the sheer volume of information to be reviewed, written, and published. The
initial complexities and challenges were such that there was a serious danger of
the project exceeding its deadline by many months, or even bogging-down
altogether without a satisfactory conclusion.
|
... a significant contribution to the development of the rail industry in Australia as
a whole. |
|
The new Safeworking Rules were distributed to the field in the form of printed manuals,
supported by online access via a dedicated web site, and managed using an
electronic document management system. The project was tightly managed to
achieve these aims. It delivered its outputs on schedule within an ambitious
timeframe, and finished $2M
under its original budget. |
The degree of consensus achieved among
stakeholders was unprecedented. The new Rules reflected the active participation
and endorsement of the Rail Tram and Bus Union, the Australian Services Union,
the Electrical Trades Union, the State Rail Authority, Freight Australia,
Pacific National, and others. It is a credit to these organisations and the
project’s management that they were able to cooperate so closely and
effectively on the important issue of safety.
The quality of the work produced has
subsequently been confirmed in an unexpected way. The Victorian Rail Authorities
are using the NSW Safeworking Rules as a model for the redevelopment of their
own safeworking processes, and the Australian Rail Track Corporation has adopted
them as benchmarks for their operations. In this way, the project has made a
significant contribution to the development of the rail industry in Australia as
a whole.
Most importantly, however, has been the
impact in the field. This is the only true test project’s success and, while
there are many important influences on safety besides knowledge and training,
the 65% reduction in the number safety incidents since the project’s
completion provides the most satisfying feedback for those involved.
|
|